A £35 million 500,000ft2 Distribution Unit with 50,000ft2 of Offices
 

·         Architect
·         M&E
·         Main Contractor

Leach Rhodes Walker
IWA
Eric Wright Construction
 

·         The Brief To design full engineering services for a modern distribution unit with through flow docks which provide a highly automated fast flow distribution unit on a fast track construction programme i.e. 10 months from design to completion.
 
·         Site Specifics The site was an old Airfield site and comprised the final phase of Heywood Business Park which had site high pressure sprinkler mains and HV distribution. Ground condition was poor and needed remediation.
 
·         Services Included lighting in aisles, hibay lighting, roof and in-rack sprinklers, jet venture heating and ventilation, guided rail fork trucks, smoke vent, fire detection, full IT and LAN networks, garage, vehicle wash, fuel station and energy centre.